OTIF
On Time In Full (OTIF)
On time in full: the share of customer order lines delivered on the agreed date and in the complete quantity.
Formula
OTIF = Order lines delivered on time and in full / Total order lines due
Worked examples
- 01Week: 1,240 order lines due, 1,108 on time and complete, 61 on time but short, 71 late. OTIF = 1,108 / 1,240 = 89.4%.
- 02Month: 4,950 lines due, 4,620 OTIF. OTIF = 93.3%.
- 03Tolerance rule: a window of 0 days early and 1 day late, quantity within plus or minus 2 percent. A line of 1,000 parts delivered with 985 counts as in full (98.5% of the quantity).
Pitfalls
- Measuring against the latest confirmed date instead of the first agreed date hides delays.
- Counting orders instead of order lines lets one big order hide many small misses.