Overall Labor Effectiveness (OLE)
The labor counterpart to OEE: availability, performance and quality of the workforce combined.
Formula
OLE = Availability × Performance × Quality
Availability = Time working / Time scheduled
Performance = Earned standard hours / Time working
Quality = Good output / Total output
Worked examples
- 01Team: 300 hours scheduled, 264 hours working (rest waiting and meetings), 240 earned standard hours, 97 percent good. OLE = 88.0% × 90.9% × 97% = 77.6%.
- 02After fixing material supply, waiting drops: 285 working hours, 255 earned hours, 97 percent good. OLE = 82.5%.
- 03Loss view: of 300 scheduled hours, 36 hours waiting, 24 hours slower than standard, and 3 percent of output not good.
Pitfalls
- Waiting for material or machines lowers OLE; it is a system loss, not a people loss.
- Wrong standard times make the performance factor meaningless.