Skip to content
Production

OEE

Overall Equipment Effectiveness

Overall equipment effectiveness: the share of planned production time in which a machine makes good parts at its ideal speed.

Formula

OEE = Availability × Performance × Quality

Availability = Run time / Planned production time

Performance = (Ideal cycle time × Total parts) / Run time

Quality = Good parts / Total parts

Shortcut: OEE = (Ideal cycle time × Good parts) / Planned production time

Worked examples

  1. 01Press 3, one shift: 450 minutes planned, 47 minutes of stops, so 403 minutes run time and availability 89.6%. Ideal cycle time 0.75 minutes, 480 parts made: performance = 0.75 × 480 / 403 = 89.3%. 456 good parts: quality = 456 / 480 = 95.0%. OEE = 89.6% × 89.3% × 95.0% = 76.0%.
  2. 02Shortcut with good parts only: a CNC cell with an ideal cycle time of 0.5 minutes made 760 good parts in 480 planned minutes. OEE = 0.5 × 760 / 480 = 79.2%. The result equals availability × performance × quality, but it does not show which loss is largest.
  3. 03Three good factors multiply down: availability 90%, performance 95%, quality 99%. OEE = 90% × 95% × 99% = 84.6%, lower than each single factor.
  4. 04Weekly view of a packaging line running three shifts on 7 days: 10,080 planned minutes, 1,310 minutes of stops, 7,120 cartons at an ideal 1.2 minutes each, 6,950 good. Availability 87.0%, performance 97.4%, quality 97.6%, OEE 82.7%.

Pitfalls

  • Using a slow "standard" cycle time instead of the ideal one inflates performance.
  • Excluding changeovers or small stops from planned time makes the number look better without any improvement.
  • Comparing OEE across machines with different definitions of planned time.

Related KPIs

Newsletter

One Lean idea.
Every two weeks.