The same machine stops every Tuesday. Maintenance repairs it, production restarts it, and the report says availability was 92 percent. Nobody counts the minor stops, the slow running or the scrap after each restart.
Total Productive Maintenance makes these losses visible and shares the work of keeping equipment healthy between the people who run it and the people who maintain it.
What the module covers
- Losses and OEE. OEE is calculated from availability, performance and quality with one written definition. Stops longer than five minutes get a reason from a short list, and minor stops are measured instead of hidden.
- Operator care. Operators clean, inspect and lubricate against a standard of ten minutes or less per shift. Abnormalities are tagged where they are found, and normal conditions are marked at the point of use.
- Planned and condition-based maintenance. Every asset has a criticality class. Preventive tasks are completed on time, measured condition triggers work on critical components and critical spares can be found within minutes.
- Problem solving and loss elimination. Breakdowns above a threshold get a root cause analysis within 48 hours. The three largest losses have owners, and lessons become one point lessons on all shifts.
- People, data and governance. The split of tasks between production and maintenance is written down, a skills matrix shows who can do what, and energy isolation rules are trained and audited.
The numbers that matter
OEE with its three factors, MTBF and MTTR, completion of planned maintenance on time, number of open tags and the share of stops with a recorded reason.
Where to start
Choose the bottleneck machine. Record stops and output during the shift for two weeks and calculate OEE honestly. Write a ten-minute operator care routine with photos and tag every abnormality you find. After thirty days you know the largest loss and have a routine that runs.
Common traps
- OEE inflated by a generous ideal cycle time.
- Operator care handed over without training or time in the shift.
- Repairs without root cause, so the same failure returns.
How it connects
TPM builds on 5S, feeds Visual and Shop Floor Management with daily losses and stabilises Flow and Just in Time. Root causes are worked in Problem Solving.
Put it into practice
Start with the free TPM Quick Start Checklist: 25 statements in five blocks, scored 0 to 4, with your result and three priorities in about 20 minutes. The Starter Kit adds a short guide, a worked example and an Excel tracker for the first 30 days in one area. The Excellence Bundle is the complete module: playbook, two-day workshop, shop floor forms, an Excel system and a ready workshop deck.