Capacity Utilization

The share of available capacity that is used by the planned or actual load.

Formula

Capacity utilization = Load / Available capacity

Worked examples

  1. 01Two machining centers on 2 shifts of 8 hours, 5 days, 85 percent availability: capacity 2 × 2 × 8 × 5 × 0.85 = 136 hours per week, load 118 hours. Utilization = 118 / 136 = 86.8%.
  2. 02Paint line: 4,800 parts per week possible, 4,150 planned. Utilization = 86.5%.
  3. 03Warehouse picking: 6 pickers × 7.5 hours × 5 days = 225 hours, workload 201 hours. Utilization = 201 / 225 = 89.3%. Above about 90 percent, waiting times rise sharply.

Pitfalls

  • Planning a bottleneck at 100 percent means queues and late orders, because variation cannot be absorbed.
  • Capacity must be defined the same way each time: with or without availability losses.