Capacity Load
Planned workload of a resource compared with its available capacity, per period.
Formula
Load = Required hours from orders / Available hours
Worked examples
- 01CNC area, week 23: 118 hours required, 2 machines × 2 shifts × 37.5 hours × 85 percent availability = 127.5 hours available. Load = 92.5%.
- 02Week 24: 162 hours required on the same 127.5 hours = 127.1%. Pulling 9.5 hours forward fills week 23 to 100 percent; the remaining 152.5 hours (119.6%) still need overtime or a third shift.
- 03Six-week view at the bottleneck: 84, 85, 96, 83, 102 and 87 percent. Average 89.5 percent, but week 5 needs action.
Pitfalls
- Using nominal capacity without availability losses.
- Looking at total load and missing the bottleneck.