Rush Order Share

The share of orders that were inserted into the schedule with less than the standard lead time.

Formula

Rush order share = Orders inserted inside the frozen period / Total orders

Worked examples

  1. 01Week: 140 orders, 23 inserted inside the 5-day frozen zone. Rush share = 16.4%.
  2. 02Cause check: 9 of the 23 came from scrap, 8 from customer changes, 6 from planning errors. Internal share = 65.2%.
  3. 03Cost: each rush order caused an average of 1.5 extra changeovers at 40 minutes = 1,380 minutes of lost capacity per week.

Pitfalls

  • Rush orders are often internal: missed parts, scrap, wrong planning.
  • The cost of a rush order is the disruption to all others.