Schedule Attainment (Plan Adherence)

The share of planned production orders or quantities completed as planned in the period.

Formula

Schedule attainment = Orders (or quantity) completed as planned / Orders (or quantity) planned

Worked examples

  1. 01Week: 64 orders planned, 55 completed in the planned week. Attainment = 85.9%.
  2. 02Quantity with cap: item A plan 400, done 460 (counts 400); item B plan 300, done 240; item C plan 200, done 200. Attainment = (400 + 240 + 200) / 900 = 93.3%.
  3. 03Without the cap the same week would show (460 + 240 + 200) / 900 = 100%, hiding the miss on item B.

Pitfalls

  • Overproducing one item does not make up for missing another; cap each line at 100 percent.
  • Changing the plan during the week and measuring against the new one.