Schedule Stability
The share of the frozen schedule that was not changed after it was released.
Formula
Schedule stability = Orders unchanged in the frozen period / Orders in the frozen period
Worked examples
- 01Frozen 2 weeks: 120 orders, 19 changed in date or quantity. Stability = 84.2%.
- 02Assembly sequence for the next 3 days: 90 positions, 6 swapped. Stability = 93.3%.
- 03Trend after introducing a frozen zone rule: 72, 81, 88 and 93 percent over four months.
Pitfalls
- Every rush order in the frozen zone costs efficiency elsewhere; make the cost visible.
- Counting only date changes and not quantity changes.