Order Lead Time

The time from receiving a customer order until it is delivered.

Formula

Order lead time = Delivery date - Order date

Worked examples

  1. 01Make to stock: order Monday, shipped Tuesday, delivered Thursday. Order lead time = 3 days.
  2. 02Assemble to order: 10 orders with 6, 7, 7, 8, 8, 9, 10, 12, 15 and 21 days. Average 10.3 days, 9th of 10 values 15 days.
  3. 03Engineer to order: 14 weeks quoted, 17.5 weeks delivered on average. Gap = 3.5 weeks.

Pitfalls

  • The quoted lead time and the real one drift apart; measure the real one.
  • Averages hide long tails; look at the 90th percentile.