Manufacturing Lead Time
The time a unit spends from release to production until it is finished, including all waiting.
Formula
Lead time = Finish time - Release time
Little's law: Average lead time = WIP / Throughput rate
Worked examples
- 01Value stream for a pump housing: 4.5 days in raw material, 1.2 days before machining, 0.8 days before assembly, 2.5 days in finished goods. Manufacturing lead time = 9.0 days.
- 02Little's law: 3,600 parts of WIP and a throughput of 900 parts per day give an average lead time of 3,600 / 900 = 4.0 days.
- 03Order tracking: released on Monday 07:00, finished on Thursday 15:00. Lead time = 3 days and 8 hours = 80 hours.
Pitfalls
- Measuring only processing times ignores the waiting that makes up most of the lead time.
- Averages hide long-running orders; track the share of orders above target.