Process Cycle Efficiency

Process Cycle Efficiency (PCE)

The share of the total lead time in which value is added to the product.

Formula

PCE = Value-added time / Total lead time

Worked examples

  1. 01Bracket: value-added time 9 minutes, lead time 6 days of 24 hours = 8,640 minutes. Process cycle efficiency = 9 / 8,640 = 0.10%.
  2. 02Office process (order entry): 25 minutes of real work, 3 days of 8 working hours lead time = 1,440 minutes. PCE = 25 / 1,440 = 1.7%.
  3. 03After a flow project the bracket lead time drops to 1.5 days = 2,160 minutes at the same 9 minutes of work. PCE = 0.42%, four times higher.

Pitfalls

  • Values below 1 percent are normal in batch production; the trend matters more than the level.
  • Lead time and value-added time must use the same time base, calendar or working time.