Availability Rate (OEE)

The share of planned production time in which the machine actually runs.

Formula

Availability = Run time / Planned production time

Run time = Planned production time - Stop time

Worked examples

  1. 01Injection molding machine 7, early shift: 450 minutes planned, 38 minutes of breakdowns, changeovers and waiting. Availability = 412 / 450 = 91.6%.
  2. 02Robot welding cell, one day with two shifts: 900 minutes planned, 126 minutes of breakdowns, changeovers and waiting. Availability = 774 / 900 = 86.0%.
  3. 03Bottleneck lathe, one week on one shift of 8 hours, 5 days: 2,400 minutes planned, 312 minutes of breakdowns, changeovers and waiting. Availability = 2,088 / 2,400 = 87.0%.

Pitfalls

  • Counting changeovers as "planned" and removing them from planned time hides the largest loss on many machines.
  • Stops shorter than a few minutes are often not logged at all.