Unplanned Downtime Rate
The share of planned production time lost to breakdowns and other unplanned stops.
Formula
Unplanned downtime rate = Unplanned stop time / Planned production time
Worked examples
- 01Line on 2 shifts: 4,500 planned minutes in a week, 315 minutes of breakdowns. Unplanned downtime = 7.0%.
- 02Plant month: 41,000 planned machine hours, 1,720 hours lost to breakdowns. Rate = 4.2%.
- 03Cost view: 315 minutes per week on a line with a margin of EUR 18 per minute of output = EUR 5,670 per week.
Pitfalls
- Classifying breakdowns as "planned" after the fact.
- Ignoring short stops below a minimum duration.