Maintenance Backlog

The amount of approved maintenance work not yet done, expressed in weeks of team capacity.

Formula

Backlog in weeks = Estimated hours of open work orders / Available maintenance hours per week

Worked examples

  1. 01Open work orders estimated at 620 hours, team of 8 technicians with 32 productive hours each per week = 256 hours. Backlog = 620 / 256 = 2.4 weeks.
  2. 02After a shutdown week the backlog grows to 980 hours = 3.8 weeks.
  3. 03Planning check: 2 to 4 weeks is often seen as healthy. At 3.8 weeks the team is close to the upper end and should prioritize before the backlog grows further.

Pitfalls

  • Open orders without hour estimates are missing from the number.
  • A very low backlog can mean that work is not being recorded.