Wrench Time
The share of a technician’s paid time spent on actual hands-on maintenance work.
Formula
Wrench time = Hands-on work time / Paid working time
Worked examples
- 01Work sampling with 400 observations: 128 hands-on work. Wrench time = 32.0%.
- 02Day of a technician: 450 minutes paid, 135 minutes searching for parts and tools, 60 minutes walking, 45 minutes waiting for release, 30 minutes meetings. Hands-on: 180 minutes = 40.0%.
- 03Effect of a parts kitting process: 60 of the 135 minutes of searching removed. Wrench time rises to 53.3%.
Pitfalls
- Measuring it to judge individuals destroys trust; it is a measure of the system.
- Travel, waiting for parts and permits are the usual losses.