Emergency Work Percentage

The share of maintenance hours spent on urgent work that interrupts the plan.

Formula

Emergency work percentage = Emergency maintenance hours / Total maintenance hours

Worked examples

  1. 01Month: 1,840 hours, 410 hours on emergency work. Emergency work = 22.3%.
  2. 02Team with 320 hours, 150 on emergencies = 46.9%: almost half of the capacity cannot be planned.
  3. 03Year trend: 31, 27, 24 and 19 percent per quarter. Reduction of 12 percentage points within the year.

Pitfalls

  • Everything becomes urgent if the priority code is not defined.
  • Short repairs done without a work order are missing.