Emergency Work Percentage
The share of maintenance hours spent on urgent work that interrupts the plan.
Formula
Emergency work percentage = Emergency maintenance hours / Total maintenance hours
Worked examples
- 01Month: 1,840 hours, 410 hours on emergency work. Emergency work = 22.3%.
- 02Team with 320 hours, 150 on emergencies = 46.9%: almost half of the capacity cannot be planned.
- 03Year trend: 31, 27, 24 and 19 percent per quarter. Reduction of 12 percentage points within the year.
Pitfalls
- Everything becomes urgent if the priority code is not defined.
- Short repairs done without a work order are missing.