Preventive Maintenance (PM) Compliance

The share of preventive maintenance tasks completed within their due window.

Formula

PM compliance = PM tasks done on time / PM tasks due

Worked examples

  1. 01Month: 186 PM tasks due, 171 done on time. PM compliance = 91.9%.
  2. 02Autonomous maintenance: 4 lines × 20 shifts × 1 checklist = 80 checklists due, 72 done. Compliance = 90.0%.
  3. 03Window rule: a monthly task due on day 15 with a window of plus or minus 3 days counts as on time if done between day 12 and day 18. 9 of 10 tasks inside the window = 90%.

Pitfalls

  • Postponing tasks and changing the due date so they never become overdue.
  • Counting a task as done when only part of the checklist was done.