PM Compliance
Preventive Maintenance (PM) Compliance
The share of preventive maintenance tasks completed within their due window.
Formula
PM compliance = PM tasks done on time / PM tasks due
Worked examples
- 01Month: 186 PM tasks due, 171 done on time. PM compliance = 91.9%.
- 02Autonomous maintenance: 4 lines × 20 shifts × 1 checklist = 80 checklists due, 72 done. Compliance = 90.0%.
- 03Window rule: a monthly task due on day 15 with a window of plus or minus 3 days counts as on time if done between day 12 and day 18. 9 of 10 tasks inside the window = 90%.
Pitfalls
- Postponing tasks and changing the due date so they never become overdue.
- Counting a task as done when only part of the checklist was done.