Dispatch Adherence

The share of jobs run at a work center in the planned sequence.

Formula

Dispatch adherence = Jobs started in planned sequence / Jobs started

Worked examples

  1. 01Bottleneck lathe: 46 jobs started in a week, 38 in sequence (within 2 positions). Adherence = 82.6%.
  2. 02Paint line: 120 jobs, 81 in sequence. Adherence 67.5%; 20 of the 39 deviations were grouping by color to save cleaning.
  3. 03Trend after fixing color groups in the plan: 67, 78, 85 and 91 percent.

Pitfalls

  • Cherry-picking easy jobs raises output and lowers delivery performance.
  • Define what counts as in sequence, for example within 2 positions.