Budget Variance
The difference between actual and budgeted cost, absolute and as a percentage.
Formula
Variance = Actual - Budget
Variance % = (Actual - Budget) / Budget
Flexible budget: Budget adjusted to actual volume
Worked examples
- 01Maintenance cost center: budget EUR 210,000, actual EUR 232,000. Variance = EUR 22,000, 10.5% over.
- 02Flexible budget: variable cost budget EUR 4.20 per unit at a plan of 180,000 units, actual 196,000 units. Flexible budget = EUR 823,200. Actual EUR 812,000 is EUR 11,200 under the flexible budget, although EUR 56,000 over the original budget.
- 03Year to date: budget EUR 2.52 million, actual EUR 2.47 million, -2.0%.
Pitfalls
- Comparing actual cost at higher volume with a fixed budget blames the plant for selling more.
- Use a flexible budget for variable cost.