Material Usage Variance

The cost effect of using more or less material than the standard for the actual output.

Formula

Usage variance = (Actual quantity - Standard quantity for actual output) × Standard price

Worked examples

  1. 01Output 12,000 housings, standard 2.4 kg each = 28,800 kg. Actual use 30,100 kg at a standard price of EUR 3.10. Variance = (30,100 - 28,800) × 3.10 = EUR 4,030 unfavorable.
  2. 02Paint: standard 0.18 liter per part, 9,500 parts, actual 1,650 liters at EUR 14. Variance = (1,650 - 1,710) × 14 = EUR -840, favorable.
  3. 03Cable: 4,000 harnesses × 6.5 m = 26,000 m standard, actual 27,300 m at EUR 0.42. Variance = EUR 546 unfavorable.

Pitfalls

  • Wrong bills of materials create variances that are not real.
  • Scrap booked elsewhere can hide usage problems.