Purchase Price Variance
The cost effect of paying a different price than the standard price for purchased material.
Formula
Price variance = (Actual price - Standard price) × Actual quantity purchased
Worked examples
- 01Aluminum: 30,000 kg bought at EUR 3.32 instead of the standard EUR 3.10. Variance = 0.22 × 30,000 = EUR 6,600 unfavorable.
- 02Fasteners: 400,000 pieces at EUR 0.041 instead of EUR 0.045. Variance = EUR 1,600 favorable.
- 03Total for the month across 180 items: EUR 6,600 unfavorable on aluminum, EUR 1,600 favorable on fasteners, others EUR 900 favorable. Net EUR 4,100 unfavorable.
Pitfalls
- Buying large lots for a better price raises inventory and its cost.
- Freight and packaging belong in the comparison.