Skip to content
Business Administration and Organization | Part 10 of 28

A Project Schedule Is a Model of Dependencies

Use critical paths, milestones and resource checks to make schedules credible and actionable.

A Gantt chart can show a precise finish date for a plan that has never been checked against available resources. The visual appearance is orderly; the delivery commitment remains weak.

A useful schedule models the work, its dependencies and the conditions required for completion. It should help management identify decisions early enough to influence the outcome.

Define completion before duration

Break the project into meaningful outputs and activities. Specify what evidence establishes that an activity is complete.

“Engineering finished” may conceal missing verification, unreleased documentation or open interfaces. If downstream work cannot safely use the output, the schedule contains a false milestone.

Involve the people who perform and receive the work. Their knowledge helps expose dependencies absent from a top-level task list.

Build the dependency logic

Identify what must precede what and why. Distinguish technical necessity from a sequence chosen for convenience.

Some activities can proceed in parallel with controlled assumptions. Others should wait because an early start creates unacceptable rework or risk.

A hypothetical equipment project can prepare site logistics while design verification continues. Releasing an unvalidated critical component may have very different consequences. The schedule should make that distinction visible.

Understand the critical path

In a basic critical-path model, the longest-duration dependency path determines the earliest modeled completion. Activities on that path have no total float under the model’s assumptions.

The path can change when durations or dependencies change. A task that was noncritical can become critical after delay.

A dependency-only calculation also assumes that required resources are available. If two tasks need the same unavailable specialist, a resource-feasible schedule may finish later.

Treat estimates as uncertain

Use evidence from comparable work and explain the conditions behind estimates. Unique tasks and unstable scope deserve explicit uncertainty.

PERT-style estimation can use optimistic, most likely and pessimistic durations to structure discussion. A calculated average is not a guarantee and does not eliminate dependencies between uncertainties.

Identify the events most capable of changing the outcome. Protect appropriate contingency and define when it can be used.

Update through evidence and decisions

Report actual completion, remaining work and changed assumptions. A percentage complete can be misleading when the difficult verification remains at the end.

Review blocked work, upcoming dependencies and the effect of changes on the complete schedule. Avoid repeatedly moving dates without resolving the cause.

If a recovery plan adds parallel work or overtime, check resources, quality and coordination. A shorter bar is not evidence that the activity has become shorter.

Make ownership practical

Give each important deliverable an owner and an acceptance route. Identify who can approve scope changes and resource tradeoffs.

Use milestones as decision points, not merely calendar decorations. A readiness milestone should establish whether the conditions for the next stage exist.

Before committing to the next major date, ask the team to trace the governing path and the scarce resources it depends on. Explain what could change the date and what action would respond.

A credible schedule improves the quality of commitments and exposes decisions while options remain available.

Newsletter

One Lean idea.
Every two weeks.