Improvement Kata and Coaching Kata | Part 1 of 6

Why Improvement Needs a Daily Routine, Not Another Workshop

Why action lists and workshop weeks go quiet after a month, and how a challenge taken out of the annual plan gives a process a direction that does not move.

Every plant has a graveyard of improvement. A workshop week with twenty actions, of which six were done. An action list in the Monday meeting that collects what is easy to agree on. A specialist who improved an area and then moved to the next one, leaving a solution behind and no skill. None of it is wrong. It simply has no mechanism that keeps it going once the attention leaves.

What usually happens

What was tried Why it goes quiet
A workshop week with twenty actions Attention leaves with the facilitator. Nobody owns the rest.
An action list in the weekly meeting The hard obstacle is reworded until it sounds solved.
An improvement target in the appraisal One push in the last quarter, not a step every week.
A specialist who improves for the area The area gets a solution and no skill. The process drifts back.
A big step that needs a decision It waits for budget, and nothing small happens either.

Improvement is a skill, not a decision, and a skill is kept by practicing it on a small, repeating task with somebody watching. That is what this series is about: a routine that the person responsible for a process and their own manager run every working day, in four parts that always come in the same order. The sequence is known from the literature on learning at the process.

The four parts

The direction comes out of the company strategy and is written as a challenge with a figure and a month. The current condition is measured at the process, not described. The next target condition says how the process will work at a date four to six weeks away. Short experiments move toward it, one change and one assumption at a time. Around all four runs a conversation of twenty minutes at the process, every working day.

The example in this series

Assembly line L3 in a plant for welded and painted steel assemblies: eight stations, six variants, 450 minutes per shift, a planned cycle of 75 seconds, demand 326 units per shift. The line produced 310 units per shift, an effective cycle of 87 seconds, with 23 line stops and five rework cases per shift, and two catch-up shifts a month.

The direction is taken, not invented

A routine without a direction is busywork, and the direction is not invented at the process. It is taken from a goal of the annual plan and translated down, in four steps, until it describes a condition of one process.

Level For line L3
Goal of the annual plan Delivery on time 98 percent, assembly cost per unit held.
What that needs from L3 The demand of the family in the customer sequence, without catch-up shifts.
The challenge, December 2028 360 units per shift at a stable cycle of 75 seconds, every variant in sequence, no catch-up shift.
The process condition behind it Nine of ten cycles within 75 seconds at every station.

A usable challenge passes five tests. Its horizon is one to three years with a month and a year. It has one figure that can be read at the process. It is clearly out of reach today and still believable. The process owner can say it from memory. And one line of the annual plan explains why it matters.

On L3 the challenge was posted at the line in one sentence, beside the record board. It did not change for sixteen weeks. What changed every few days was the next step, which is the subject of the rest of this series. It starts where every routine has to start: with a measured current condition.