Reorder Point Calculator
The inventory level at which a new order has to be placed, and whether today is the day.
Enter your figures and select Calculate. The fields are prefilled with a worked example.
How to read it
How it was calculated
Please confirm your newsletter subscription via the link in your inbox.
The formula
Use this calculator when you manage a part with a fixed order quantity and need the level that triggers the next order.
Reorder point = Average demand × Lead time + Safety stock
Inventory position = Stock on hand + Open orders
Worked example
Inputs
- Average demand per week: 400 units
- Lead time: 4 weeks
- Safety stock: 885 units
- Stock on hand: 1,900 units
- Open orders not yet received: 400 units
Calculation
- Demand during lead time = 400 units × 4 = 1,600 units
- Reorder point = 1,600 + 885 = 2,485 units
- Inventory position = 1,900 on hand + 400 on order = 2,300 units
- Position minus reorder point = 2,300 - 2,485 = -185 units
Result
Reorder point: 2,485 units. The inventory position of 2,300 units is at or below the reorder point of 2,485 units: place the order now. Every week of delay eats 400 units of the safety stock.
How to read the result
- Compare the reorder point with the inventory position, not with the stock on hand. Otherwise every part that is waiting for a delivery gets ordered twice.
- Use the real lead time from order to availability on the shelf, including goods receipt and inspection.
- Review the reorder point when demand or lead time shifts. A reorder point set years ago is one of the most common causes of both shortages and excess stock.
- Kanban Card Count
The number of kanban cards or containers a loop needs: demand during the replenishment lead time plus safety, divided by the container quantity.
- Safety Stock
The stock that protects a service level against variation in demand and in lead time.
- Inventory Turns and Days on Hand
How often the inventory turns per year, how many days it covers and what holding it costs.