Skip to content
Free calculator | Inventory and replenishment

Kanban Card Count Calculator

The number of kanban cards or containers a loop needs: demand during the replenishment lead time plus safety, divided by the container quantity.

Your figures

units
days

From the card being released until the full container is back: waiting, production, transport.

%

Allowance for demand peaks and supply disturbances.

units

Calculated in your browser. Your figures are neither transmitted nor stored.

Enter your figures and select Calculate. The fields are prefilled with a worked example.

The formula

Use this calculator when you set up or resize a kanban loop for a part with steady demand.

Kanban cards = Demand per day × Replenishment lead time × (1 + Safety factor) / Container quantity (rounded up)

Worked example

Inputs

  • Demand per day: 600 units
  • Replenishment lead time: 1.5 days
  • Safety factor: 15%
  • Container quantity: 50 units

Calculation

  1. Demand during replenishment = 600 units per day × 1.5 days = 900 units
  2. Safety stock = 900 units × 15% = 135 units
  3. Kanban cards = (900 + 135) / 50 = 20.7, rounded up to 21
  4. Maximum inventory = 21 × 50 = 1,050 units = 1.75 days of demand

Result

Kanban cards: 21 cards. The loop needs 21 cards. Always round up: rounding down removes the safety you just defined. The inventory in the loop can never exceed 1,050 units, which is the point of the card limit.

How to read the result

  • Use consistent units: demand per day needs a lead time in days. Include waiting and transport in the replenishment time, not only the processing.
  • Recalculate when demand, lead time or container size changes, and count the cards regularly. Lost cards silently shrink the loop.
  • Reduce the number of cards step by step once the replenishment has become shorter or more reliable, not as a way to force improvement.
Newsletter