A Lean plant levels its production and runs Kanban loops. A planning department runs S&OP. Often the two never meet, and the plant keeps fighting peaks that the plan could have smoothed months before.
S&OP and Lean are not competing approaches. They are levels of one system.
Four levels
- S&OP, 18 months, family and month: how much per family, which capacity, which inventory targets.
- Master schedule, 8 to 12 weeks, item and week: which items in which week, within the S&OP volume.
- Leveling, 1 to 4 weeks, item and day: how evenly per day, in a repeating mix pattern.
- Execution, shift, order and hour: Kanban, sequence, the shop floor board.
Each level works inside the frame of the level above. The master schedule may shift mix but not the family volume decided in S&OP. Leveling smooths the master schedule into daily quantities.
From monthly volume to a daily pattern
The executive review approved 2,500 compact pumps for June 2027. With 20 working days, that is 125 pumps per day. The master schedule splits the family into variant groups: A 60 percent, B 30 percent, C 10 percent. The daily pattern becomes 75 A, 38 B and 12 C, produced in small repeating batches.
Without S&OP, the plant sees the June volume only when the orders arrive. With it, the daily rate is known months ahead, and staffing, material and loop sizes can follow.
Kanban sizing follows the plan
Kanban loops are sized for a planned daily demand. In January the plan was 110 compact pumps per day, in June 125, an increase of 13.6 percent. Loops sized in January would run empty in June.
The rule: when S&OP changes the daily rate of a family by more than 10 percent, recalculate the cards. The supply review lists the families where this happens, and the loop owners adjust before the change reaches the line.
Pre-building is leveling over months
Leveling is usually explained within a day or a week. S&OP applies the same idea across months. The decision to pre-build 250 compact pumps in January and February each and take them out of April and May is leveling on a larger scale. It keeps the load between 95 and 105 percent instead of between 93 and 111 percent.
Feedback upward
The shop floor reports back. Schedule adherence, real output per day and capacity losses flow into the next supply review. If assembly reaches only 9,200 of the planned 9,500 hours for three months, available capacity in the plan is lowered, and the gap becomes visible before it hurts.
One system
S&OP decides how much. Leveling decides how evenly. Kanban decides when to replenish. A company that runs only one of the three keeps fighting the other two. A company that connects them gets a plant that runs calmly, because the big decisions were taken early, at the right level, by the right people.