A quote in industrial business costs hours of the people a company has least of: application engineers, calculators, experienced inside sales. A check decides where those hours go.
The starting point
The example company, a maker of hydraulic power units, received 2,000 inquiries last year, wrote 1,200 quotes and won 264 orders: a hit rate of 22 percent. Each quote took 9 hours, 10,800 in total, 40.9 hours per order won.
Nobody had chosen which inquiries to quote. Every inquiry was a chance, so each got a quote while someone had time. The other 800 were never declined, only left until the customer stopped asking.
Eight questions
The company wrote its own check with two sides: do we want it, and can we win it?
Fit:
- Application: known in our range, or a wanted new one?
- Customer: class by potential, segment we want to grow in?
- Margin: is the expected price level above our floor?
- Delivery: can engineering and production meet the date?
Chance:
- Project: a real project with a date and a budget level?
- Access: do we talk to the people who specify and decide?
- Position: did we shape the specification, or only fill a comparison list?
- Record: have we won here before, or lost five times in a row?
Each question scores 0 for no or unknown, 1 for partly, 2 for clearly yes.
| Points | Proposal | What happens |
|---|---|---|
| 10 to 16 | Go | Stage 1, with an owner |
| 7 to 9 | Check | Sales manager decides the same day |
| 0 to 6 | No-go | Polite answer within two working days |
The questions and limits are the company’s own; set yours from your won and lost quotes.
Two inquiries of one week
Customer AC-103 asks for a servo press drive for a new press line, EUR 320,000. Design wants a concept talk, the decision comes in three months. Fit 7 of 8, chance 6 of 8: go with 13 points.
An unknown trading company asks for two special units within three days, the specification naming another supplier’s part numbers. Fit 2 of 8, chance 1 of 8: no-go with 3 points.
Rules that keep the check honest
- Knock-out points: no quote without a named contact, a realistic date or a price above the floor.
- Effort limit: the check applies above two hours of quoting; below that inside sales quotes from the standard range.
- A second look: A customers get a conversation before a no-go.
- Feedback: each quarter the scores of won and lost quotes are compared and the limits adjusted.
How to decline
A no-go is an answer, not silence. Within two working days the customer hears that the company will not quote this request, why in one sentence, and what it can offer instead: a standard unit, a later date or a contact for the next project. Of the 650 inquiries declined in year one, 41 came back with a fitting request.
What changed in twelve months
| Last year | Year one | |
|---|---|---|
| Declined within two working days | None | 650 |
| Quotes submitted | 1,200 | 900 |
| Orders | 264 | 270 |
| Hit rate | 22 % | 30 % |
| Hours for quotes | 10,800 | 9,000 |
On the same 2,000 inquiries the company wrote 300 quotes fewer and won 6 orders more. Hours per order fell from 40.9 to 33.3. The saved hours did not disappear: the application engineers had time for concept talks, so the average quote took 10 hours instead of 9 and carried an agreed concept, a confirmed date and a calculated benefit.
The hard part
The check takes ten minutes. What makes it work is that someone may say no and that the sales manager stands behind it when a customer complains. Start with ten current inquiries: score them in silence, then discuss the differences.