Digital Shop Floor | Part 6 of 10

Digital Work Instructions That Get Used

The right instruction for this order, at this station, in the current version. Why scanning the paper is not enough.

The quickest way to digitize work instructions is to scan the paper folders and put a tablet at every station. It is also the quickest way to make sure nobody reads them. An instruction that was ignored on paper will be ignored on a screen.

Digital work instructions are useful when they are rewritten for the station and linked to the order.

Five rules

  • Pictures and short text, one step per screen. Readable at arm length, with gloves, by people with different first languages.
  • Linked to the order and the variant. The operator does not search. The station shows the instruction for the part in front of it, and wrong variants become hard to build.
  • Versioned with one owner. A change is released by the owner, and the old version disappears from every station at the same moment.
  • Key checks confirmed at the step. Torque, orientation or a visual check are recorded where they happen, not ticked off at the end.
  • A feedback button. When an instruction is wrong, the operator reports it in two touches and the owner sees it the same day.

Write for the station

A good instruction starts from standard work: the sequence, the key points and the reasons for them. If the standard is unclear, digitizing it only makes the confusion faster. Update the standard first, then build the screens.

Take pictures at the real station with the real parts. Mark the key point in each picture: the edge to check, the direction of a connector, the position of a label. Keep the text to one line per step.

From change request to the station

Changes follow three steps:

  1. Request: an operator, engineer or quality inspector reports the needed change.
  2. Change: the owner updates steps and pictures, a second person checks at the station.
  3. Release: the new version goes live everywhere at once, and the team is briefed in the daily meeting.

This replaces the familiar situation in which three versions of the same instruction hang in three places.

Where to start

Start where variants and errors are frequent: assembly with many variants, rarely built products, new operators during ramp-up. A machining center with one part family for years needs a setup sheet, not a step-by-step guide.

Measure use

Count instructions opened per order, feedback messages per month and the time from feedback to release. Watch the errors that the instruction should prevent. If assembly errors on a variant do not fall within a few weeks, go to the station and watch how the instruction is used. The answer is usually in front of the screen, not inside it.