Contractor Safety: Site Briefing, Work Clearance and Special Work

Contractors and non-routine work: briefing before the start, a written clearance in the plant own wording, and checkpoints for hot work, height and confined spaces.

Contractors do the most unusual work in a plant: on roofs, inside tanks, with open flames. And they know the plant least.

Duties of the client and the contractor, required permits and qualifications are regulated in most countries and differ widely. Clarify them with your safety professional. The clearance form described here is the example plant’s own, in its own wording. It is not an official permit.

An event that started it

Month 6 in the example plant: a contractor cuts a bracket with a grinder in Hall 1. Below him, cardboard is stored. Sparks fall onto it. A forklift driver sees it and stops the work.

The investigation found no careless contractor. It found that nobody in the plant had known on which day the work would take place, that there was no contact person, and that the requester had assumed the contractor “knows what to do”. The main cause went into the register as work organization and planning.

Five steps

Before the order. Scope of work, hazards from the work and from the plant, qualifications asked for.

Before work starts. A site briefing: routes, alarm, first aid, rules of the plant, the contact person. Signed by everyone on the job.

Work clearance. A written clearance for this job, this place and this day, with the agreed measures. Issued by the manager of the area in which the work takes place, because that manager knows what else happens there.

During the work. The contact person, one named employee per job, visits the work site at least once per day. A deviation stops the work until it is fixed.

After the work. The place is handed back, guards and fire protection are restored, the clearance is closed.

What the clearance asks

The form of the example plant is one page. At its center are two fields side by side: hazards from the work, and hazards from the plant at this place. The first is filled in by the contractor, the second by the area manager. Below them: the agreed measures, each with a name.

Special work as checkpoints

Some kinds of work get additional points on the clearance. The example plant uses these, as its own list.

Hot work: combustible material removed or covered, an extinguisher at hand, a fire watch during and after the work, detectors handled by an agreed rule.

Work at height: fixed access or a platform before a ladder, edge protection, anchor points checked, the area below closed off, rescue thought through.

Confined spaces: atmosphere tested, energy and inflow isolated, a second person outside, a way to get the person out.

The same rules for your own people

Special work is not safer when the plant’s own maintenance does it. In month 8 a ladder slipped during a lamp change at four meters in Hall 3. The technician held on to a beam. The measure was on the substitute level: a mobile work platform replaces ladders above two meters, a value the plant chose for itself.

Year one in numbers

Item Value
Contractor companies 14
Work clearances issued 61
Of these general 42
Hot work 9
Work at height 7
Confined space 3
Clearances checked at the work site 55
Deviations found, work stopped until fixed 6

Ninety percent of the clearances were checked at the work site. Six deviations in 55 checks is about one in nine.

What to do this week

Find out which contractors are in your area today and what they are doing. If you need more than two phone calls to answer that, start with a simple rule: no contractor job begins without a named contact person and a signature from the area manager.