Sales and Operations Planning | Part 2 of 10

Plan in Families, Months and Time Fences

Product families make the S&OP plan readable, and frozen, firm and open zones make it stable near today and flexible further out.

The first S&OP meeting of many companies opens a spreadsheet with 3,000 item numbers. After an hour the team has discussed twelve of them, and nobody has looked at capacity in May.

Before the first cycle, three structural decisions are needed: product families, planning units and time fences.

Families by demand and by resource

A product family groups items that sell to similar customers with a similar demand pattern and use the same bottleneck. Five to fifteen families are enough for most business units.

The pump manufacturer uses three:

  • Compact pumps, make to stock: 140 variants, 2,200 to 2,700 units per month, 1.5 assembly hours each.
  • Process pumps, assemble to order: modules in stock, final assembly to order, 600 to 680 units per month, 6 hours each.
  • Engineered systems, engineer to order: 16 to 20 skid systems per month, 120 hours each.

The strategy of each family decides what the plan controls. For compact pumps it is finished stock. For process pumps it is modules and assembly capacity. For engineered systems it is engineering and assembly hours reserved for projects.

One planning unit per family

Each family is planned in one unit: pieces, tons, meters or projects. Fixed factors turn the unit into hours on the bottleneck and into money. With those factors, one number per family and month is enough to check capacity and revenue.

Every item number is mapped to exactly one family. The mapping lives in one table owned by the demand planner. Change the family structure once a year at most, because every change breaks the history.

Three zones

The plan looks far ahead and changes little near today. Time fences make this explicit:

  • Frozen, weeks 0 to 2: nothing changes, except emergencies with a written reason, decided by the plant manager.
  • Firm, weeks 3 to 8: mix within the family can change, volume within plus or minus 10 percent, decided by the master scheduler with sales.
  • Open, week 9 to month 18: volume, mix, capacity and inventory targets, decided in the executive review.

The firm zone must cover the longest reaction time that matters. In the example, cast pump housings have six weeks of lead time, so the firm zone ends at week 8.

Requests inside the fences

The fences are useful only if everybody applies them. A customer wants 80 extra compact pumps next week: that is the frozen zone, so they come from stock or the plant manager and sales decide on priority. A mix change in week 5 is accepted if parts are available. Plus 15 percent process pumps in week 6 is outside the firm limit and goes into the next supply review with options and cost.

Rules like these end the daily negotiation between sales and the shop floor. They also show sales where an early signal is worth more than an urgent call.

With families, units and fences in place, the first demand review can discuss the real question: how much per family and month, and why.