A pump manufacturer delivers 84 percent of its orders on time and in full. At the same time it holds 20 days of finished stock in its standard pumps and runs overtime every quarter end. Sales blames operations, operations blames the forecast, and finance finds the gap to the budget at month end.
Nobody in this company is doing a bad job. The company simply has no place where volume decisions are taken early and together.
What S&OP is
Sales and operations planning is a monthly decision process for the management team. Once a month the people who own the numbers look 18 months ahead, compare what the market wants with what the company can supply, and decide how to close the gap while options are still cheap.
It works in product families and months, not in item numbers and shifts. Detailed scheduling stays where it belongs, in planning and on the shop floor.
Five steps, fixed dates
A cycle has five steps, each with a chair and a result:
- Data and portfolio, week 1: actuals closed, forecast accuracy calculated, new products and phase outs reviewed.
- Demand review, week 2: the sales plan and the statistical forecast reconciled into one demand plan with written assumptions.
- Supply review, week 3: capacity, critical materials and inventory targets checked, options for every gap.
- Pre-S&OP, week 4: volume and money reconciled, scenarios and decision proposals prepared.
- Executive review, week 4: the general manager decides. One plan for the whole company.
Put twelve months of dates into all calendars before the first cycle. A process without fixed dates becomes a meeting when someone has time.
What it is not
S&OP is not a forecast made by operations because sales will not make one. It is not a meeting that reviews last month. It is not a software project, and it is not the annual budget.
The test is simple: did the last executive review take a decision that changed volume, capacity, inventory or money? If not, the company has a planning meeting, not S&OP.
Why the horizon is 18 months
A budget year ends in December. Customers, capacity and suppliers do not. A rolling horizon of 18 months always shows the next budget year before it is set, and it shows a capacity problem in May while it is still January.
In the example, assembly needs 111 percent of its hours in May and only 93 percent in January. Three months ahead, the company can pre-build standard pumps in January. In the week itself, only overtime and expediting are left.
Who owns it
The general manager chairs the executive review. Sales owns the demand plan, operations owns the supply plan, finance owns the translation into money. A process owner runs the cycle and keeps the decision log.
When operations runs S&OP alone because it suffers most, it stays a capacity meeting. The process works when every department brings its number and the general manager decides on the gaps between them.