Cost Performance Index
Cost Performance Index (CPI)
Earned value divided by actual cost: how efficiently the budget is turned into completed work.
Formula
CPI = Earned value / Actual cost
Estimate at completion (EAC) = Budget / CPI
Worked examples
- 01Week 16: earned value EUR 740,000, actual cost EUR 790,000. CPI = 0.94.
- 02Forecast: budget EUR 1,710,000 / 0.9367 = EUR 1,825,541.
- 03With the CPI rounded to 0.94 the estimate is EUR 1,819,149, inside a contingency of EUR 140,000.
Pitfalls
- Late booking of invoices makes CPI look better than it is.
- A CPI above 1.0 early can mean work is underestimated.