Cost Performance Index

Cost Performance Index (CPI)

Earned value divided by actual cost: how efficiently the budget is turned into completed work.

Formula

CPI = Earned value / Actual cost

Estimate at completion (EAC) = Budget / CPI

Worked examples

  1. 01Week 16: earned value EUR 740,000, actual cost EUR 790,000. CPI = 0.94.
  2. 02Forecast: budget EUR 1,710,000 / 0.9367 = EUR 1,825,541.
  3. 03With the CPI rounded to 0.94 the estimate is EUR 1,819,149, inside a contingency of EUR 140,000.

Pitfalls

  • Late booking of invoices makes CPI look better than it is.
  • A CPI above 1.0 early can mean work is underestimated.