Schedule Performance Index
Schedule Performance Index (SPI)
Earned value divided by planned value: how much of the planned work has actually been done.
Formula
SPI = Earned value / Planned value
Earned value = Budget × Percent complete
Worked examples
- 01Week 16: planned value EUR 820,000, earned value EUR 740,000. SPI = 0.90.
- 02Work package: budget EUR 180,000, 63 percent done, planned to be 75 percent done. EV = EUR 113,400, PV = EUR 135,000, SPI = 0.84.
- 03Rough time effect: an SPI of 0.90 on a 29-week plan suggests about 29 / 0.90 = 32.2 weeks if nothing changes.
Pitfalls
- Percent complete by feeling makes SPI meaningless; define milestones or rules.
- SPI drifts to 1.0 at the end of every project, even late ones.