Ramp-Up Time
The time from start of production of a new product or line until it runs stably at target output and quality.
Formula
Ramp-up time = Date target is reached - Start of production date
Target, for example: OEE and first pass yield at target for 5 days in a row
Worked examples
- 01New line starts production on 4 March, reaches 80 percent OEE and 98 percent first pass yield for 5 days on 29 April: ramp-up = 8 weeks.
- 02Volume curve: target 900 units per day; week 1 300, week 2 480, week 4 690, week 6 860, week 8 910. Week 6 is at 95.6%.
- 03Lost output during ramp-up: planned 900 per day over 8 weeks of 5 days = 36,000 units, actual 27,400. Gap = 8,600 units.
Pitfalls
- Define the target before the launch, not afterwards.
- Reaching output with overtime and sorting is not a stable ramp-up.