Production System | Part 13 of 16

Launch Management: New Products at Target Quality from Day One

Phases and gates, team and issue management, readiness, trial runs and ramp-up: how to launch without months of firefighting.

The new product starts on time. For the next four months the line runs at half speed, first pass yield is far below target and the best people spend every day firefighting. The launch met its date but missed its purpose.

Launch Management treats a launch as a managed process with clear gates, a cross-functional team, readiness checks and a ramp-up that is planned in numbers.

What the module covers

  • Phases and gates. Written phases from release to stable series production. A gate is passed only when its exit criteria are met or open points have an owner and a date. Gate reviews happen at the line.
  • Team, status and issues. A launch manager with written authority and enough time, all functions represented, a weekly status with one traffic light per workstream and issues that escalate by rule when they age.
  • Readiness. Operators are trained on released standards, equipment is accepted against written criteria, every part has a released source and supply route, and critical suppliers have passed a readiness check.
  • Trial runs and ramp-up. Every trial run has a plan and a written result. A ramp-up curve sets planned output and first pass yield per week, and the exit from ramp-up is defined in numbers.
  • Learning and data. Lessons are recorded during the launch and reviewed at the next kickoff. Ninety days after handover a review checks the targets.

The numbers that matter

Gate criteria met on time, open issues by age, output and first pass yield against the ramp-up curve, and the time from start of production to stable series output.

Where to start

Take the next launch on the calendar. Write the gates and exit criteria on one page, name the launch manager and set up the weekly status with one traffic light per workstream. Review the lessons of the previous launch at the kickoff. Thirty days in, the issue list shows where readiness is weakest.

Common traps

  • Passing gates to protect the date while criteria are open.
  • A launch manager without authority or time.
  • Lessons learned that are written but never read.

How it connects

Launch Management uses Standard Work and Zero Defects to prepare the line, Intralogistics and Material Flow for supply and Problem Solving during ramp-up.

Put it into practice

Start with the free Launch Management Quick Start Checklist: 25 statements in five blocks, scored 0 to 4, with your result and three priorities in about 20 minutes. The Starter Kit adds a short guide, a worked example and an Excel tracker for the first 30 days in one area. The Excellence Bundle is the complete module: playbook, two-day workshop, shop floor forms, an Excel system and a ready workshop deck.