The share of actions from meetings, audits or problem solving that are completed by the due date.

Formula

Action completion = Actions closed on time / Actions due

Worked examples

  1. 01Week: 38 actions due, 29 closed on time. Completion = 76.3%.
  2. 02Overdue: 9 actions, 4 of them older than 30 days.
  3. 03Month: 152 actions due, 131 closed on time = 86.2%.

Pitfalls

  • Moving the due date counts as on time in many lists; keep the original date.
  • Closing actions without checking the effect.