Milestone Hit Rate

The share of project milestones reached on the planned date.

Formula

Milestone hit rate = Milestones reached on time / Milestones due

Worked examples

  1. 01Portfolio quarter: 46 milestones due, 35 on time. Hit rate = 76.1%.
  2. 02One project: 12 milestones, 9 on time, 2 within one week, 1 four weeks late. Hit rate 75%.
  3. 03Gates only: 8 of 9 gates on time = 88.9%.

Pitfalls

  • Re-planning a milestone before it is due and counting it as on time.
  • Small milestones count as much as a gate; weight if needed.