Milestone Hit Rate
The share of project milestones reached on the planned date.
Formula
Milestone hit rate = Milestones reached on time / Milestones due
Worked examples
- 01Portfolio quarter: 46 milestones due, 35 on time. Hit rate = 76.1%.
- 02One project: 12 milestones, 9 on time, 2 within one week, 1 four weeks late. Hit rate 75%.
- 03Gates only: 8 of 9 gates on time = 88.9%.
Pitfalls
- Re-planning a milestone before it is due and counting it as on time.
- Small milestones count as much as a gate; weight if needed.