Nobody can redesign fourteen processes at once. The first decision in process management is which process comes first, and the second is where it starts and ends.
Four criteria for the choice
Score every process on the map from 1 to 5 on four criteria.
- Volume. A few cases per year score 1, several cases per day score 5.
- Effect on the customer. Does the customer wait for the result or see every error?
- Trouble today. Queries, complaints, overtime, escalations.
- Chance of success. Can the people in the room change it within three months, without a new system or another site?
Customer effect and trouble count double. The score is volume plus two times customer plus two times trouble plus chance, 30 at most.
| Process | From, to | Score |
|---|---|---|
| Process orders | Inquiry to invoice | 29 |
| Serve customers | Complaint or request to closure | 24 |
| Plan and produce | Order release to goods issue | 23 |
| Procure | Demand to payment | 22 |
| Engineering change | Request to effective date | 22 |
In the valve plant, order processing won clearly: 4,800 cases per year, direct contact with the customer at three points, 60 queries per 100 orders and six roles on one site who could change things themselves.
Four borders
Once the process is chosen, it needs borders. Four questions set them.
- Trigger. Which event starts a case? For order processing: an inquiry of a customer arrives.
- Result. What exists when the case is finished? The correct invoice is sent and the order is closed.
- Customer. Who receives the result, and who inside the plant depends on it? The external customer, and inside the plant production planning and finance.
- Extent. Which cases are in, which are out? In: configured valves from the standard range. Out: projects above EUR 250,000, spare parts orders and production itself.
The discussion about these four points regularly takes an hour, and it is the most useful hour of the whole analysis. Whether the process starts with the inquiry or with the order decides whether the quote is part of the problem. In the example, 6.5 of the 15.7 days of office lead time were spent before the order even existed.
Production is excluded on purpose: the clock stops while the valve is made and while the customer decides.
The process profile
The answers go onto one page, the process profile. It contains:
- Name, from trigger to result, and the number on the process map
- Trigger, result and customers
- What is in scope and what is out of scope
- Cases per year
- Roles involved, systems and media used
- Key figures today, as far as known
- Targets with a date
- Process owner and sponsor, with signatures
The profile of the example names 4,800 orders per year, six roles, five systems and media from e-mail to the ERP system, and two targets: office lead time below 6 days and first pass rate above 80 percent.
The right size
A first process should be small enough to capture in one day and large enough to matter. Three to eight roles and eight to twenty steps are a good size. If the scope produces forty steps, cut it: take one product group, one region or one section of the path.
Why the signature matters
The sponsor signs the profile before the analysis starts. This is not a formality. With the signature, management confirms the scope, frees the people for the workshop and accepts that the result may change rules that management itself has set, such as approval levels.
In the valve plant, the managing director signed the profile and named the head of order management as process owner on the same day. The next part shows how the current process gets from the heads of the people onto a wall.