Most plants have more reports than they read. The monthly plant report should be the one everybody reads: two pages, the same every month, operational and cost KPIs side by side.
What goes on two pages
| Area | KPI |
|---|---|
| Cost | Manufacturing cost per good part |
| Productivity | Good parts per paid direct hour, OEE of the bottleneck |
| Quality | Scrap rate and cost of scrap |
| Delivery | On-time delivery |
| Inventory | Inventory value and days |
| Budget | Variances by cause, with actions |
Each KPI has a target, the last months as a trend and one line of comment. In the example plant the first quarter of 2027 looked like this: manufacturing cost per part 28.79, 28.74 and 29.31 euros against a target of 28.44; scrap 2.9, 2.8 and 3.4 percent; OEE on the bottleneck 71, 72 and 69 percent. The March spike has one story, the porous castings, and the report tells it once.
The meeting, sixty minutes
- Prepared. Both sides read the report before the meeting. Nobody presents numbers.
- The three largest variances. Cause, action, owner, date.
- Last month’s actions. Done, and did they work?
- Forecast. Where will we land at year end, and what can we still change?
- Decisions. What does plant management need to decide?
The rule of the room: discuss causes, not numbers. The controller explains how a number is made. The area manager explains what happened at the machine. Nobody defends.
Typical disagreements
- “The rate is too high, the machine is new.” Agree the rule for running hours and depreciation once, for all machines.
- “The improvement saved EUR 200,000.” Separate cash and capacity, and check after six months.
- “Overhead is not my business.” Show which overhead the area causes: maintenance hours, quality checks, logistics moves.
- “The report is late and wrong.” Fix the source data at the machine and in the bookings first, then the deadline.
The 2026 layer
Energy prices and carbon costs now move more than wages, so energy per good part belongs on the report. Machine data and shop floor bookings can feed it directly, which removes spreadsheets and versions. AI assistants help draft variance comments and spot outliers, but the owner still checks the cause at the machine.
Next step: value stream costing
Many lean plants go one step further and collect costs by value stream instead of by department. Material, people, machines, space and supplies of one stream are collected with few allocations, and the cost per unit of the stream shows the effect of improvements directly.
It works best with stable value streams and dedicated resources. Start with a shadow report next to the existing cost centers before changing the accounting.
What makes it work
Not the template. The rhythm. Twelve meetings in the calendar, the same agenda, actions with owners, and two people who decide to look at the same page together.