Incoming Inspection and Traceability | Part 5 of 6

Skip Lot and Supplier Release: Reducing Inspection on Evidence

What a supplier has to show before incoming inspection is reduced or skipped, how the release is written, and how it ends the moment a lot is rejected.

Reducing incoming inspection is the payoff for everything else in this series. It is also the step most plants take badly: somebody notices that the last few lots from a supplier were fine, the checks quietly stop, and nobody can say later when or why.

A release is earned with records, written down, and withdrawn without discussion.

Four things to check before a release

The record. Twenty accepted lots in a row, no complaint, and a defect rate inside the agreed range. Twenty is not a magic number, but it is enough that a run of luck is unlikely, and it is countable from the receipt log without anyone’s opinion.

The process. A part approval on file for the current revision, with capability shown for the critical characteristics. A supplier whose lots pass your sample but whose process has never been demonstrated is a supplier whose next lot is a coin toss.

The agreement. The switching rules, the duty to report a process or source change before it ships, and the cost of an escape, all signed. A release that the supplier has not signed is a decision you made alone.

The trace. The supplier can name, for one of their lots, which of your receipts it went to. If they cannot, the release is premature, because the first problem will take days to contain.

The four states

A supplier sits in exactly one state at a time, and the state is visible on one sheet.

New. The first three lots are inspected in full against the approved sample. No exceptions for a rush.

Normal. The plan of the risk class applies to every lot.

Reduced. The sample is halved after ten accepted lots and six months without a complaint. One rejection ends it.

Skip lot. One lot in four is inspected, on a written release. One rejection ends it, and the supplier returns to normal, not to reduced.

A fifth state, blocked, exists for the case where a defect reached the customer: every lot is inspected, at the supplier cost, until the fix is proven on three lots.

What it looked like after twelve months

Status Suppliers Receipts per year
New 3 96
Normal 31 2,592
Reduced 19 2,352
Skip lot 11 720
Blocked 0 0

Of 5,760 receipts a year, 720 are on skip lot and 2,352 on reduced inspection. Every step is backed by a counted record, and every step ends on one rejection.

The sheet carries one more column that is worth the effort: the status the record suggests, calculated next to the status in force. When the two disagree, somebody either released a supplier too early or forgot to release one that earned it. Both are worth five minutes a month.

Why the trigger must be the record

A switching rule that depends on judgment gets argued about at exactly the moment nobody has time: a line is down, the replacement lot is in the truck, and the supplier is on the phone.

If the trigger is the log, there is nothing to argue. The sheet shows twenty accepted lots, so the sample halves. The sheet shows a rejection, so the release ends and the next lot is inspected in full. The supplier was told this before the release was signed, so the call is short.

The plant in the example released its first eleven suppliers to skip lot in month nine. Two of them came back to normal inspection within a year, both after a single rejection, and both returned to skip lot later. Nobody had to negotiate either move.