In the valve block plant, material took 3.2 days from the arrival of the truck to the moment it was available in its stock location. The inspection itself took 0.1 days. Everything else was queue.
Inspection does not slow a plant down. Waiting for inspection does. Treat the receiving area like any other process with a queue, and most of the time disappears without anyone working faster.
Where the three days went
| Step | Before | After |
|---|---|---|
| Truck to the receiving counter | 0.3 days | 0.3 days |
| Waiting for the inspection round | 2.4 days | 0.2 days |
| Inspection itself | 0.1 days | 0.1 days |
| Booking and putaway | 0.4 days | 0.3 days |
| Dock to stock | 3.2 days | 0.9 days |
Two changes produced almost all of it. Class C material, 55 percent of the receipts, stopped queuing at all: it is cleared at the counter with an identity, quantity, document and condition check, then booked straight to stock. And the inspection round moved from once a day to twice a shift, so a lot that misses one round waits hours instead of a day.
Five things the area needs
A marked place with light and a table at working height. A lot inspected on the floor takes twice as long and is inspected worse. Two stations of 1.8 by 2.4 meters were enough for 24 receipts a day.
The gauges of the plans, at the place. Every walk to the measuring room adds half an hour and tempts the inspector to skip a characteristic. If a plan names a gauge, the gauge lives at the station.
A sequence rule. The next lot is the oldest one, with class A ahead of class B, and urgent lots follow a written rule rather than whoever shouts. Without a rule the sequence is decided at the counter, and two lots are forgotten in a corner every week.
A place to wait. Twenty-four racked and labeled places, visible from the counter. Material standing in a gangway is counted twice, moved three times and found last.
A blocked area. Separate, locked, with its own labels. Rejected material that can be picked by mistake is not rejected, it is delayed.
Capacity, not goodwill
Inspection capacity is planned like any other capacity: expected receipts per class multiplied by minutes per receipt, against the hours of the people who do the work. In the example that is 2,160 inspected receipts and 864 hours a year against two inspectors, which leaves room for the special requests that always come.
A plan with no slack produces a queue on the first bad day, and the queue never clears, because the next day brings its own receipts. If the arithmetic says the area is full, either the scope is too wide or the staffing is too thin. Both are decisions someone has to make, and both are easier to make with the number in front of them.
Measure the right thing
Two figures belong on the board in the receiving area.
Dock to stock per receipt, as an average and as a longest value. The longest value is the one that tells you something: an average of one day with a longest of fourteen means one part family is being forgotten.
And the number of lots waiting, counted at the same time every day. When that number grows for three days in a row, something upstream has changed, and it is easier to find now than at the end of the month.
Neither figure needs a system. A clipboard at the counter and two columns in a spreadsheet produce both of them, and the discussion they start is worth more than the measurement.