Operational Risk Management | Part 6 of 8

Continuity Planning: Target Restart Times and Exercises

Six scenarios that would stop a plant, what a plan has to contain, and why four half-day exercises find more than a year of writing.

A measure makes an event less likely or smaller. A plan makes the first day shorter. Both are needed, and only one of them can be exercised.

What a plan contains

Six parts, one page. The trigger: what has to be true for the plan to start, and who declares it. The target restart time: when deliveries to the customer run again, in days or hours, agreed with sales. The first steps: the first six actions in order, each with a name, not a department. The people to call: internal and external, two numbers each, checked twice a year. The resources: a partner, a buffer, a generator, a hall, a transport loop, a license. And the return to normal: how the plant goes back, and who confirms that it has.

The baseline belongs next to the target. It is where you stand today, without a plan, and the distance between the two is the work.

Six scenarios

Scenario Target restart Baseline
Housing line down, MC-200 out for more than three days 5 days 18 days
Motor supply stops, no delivery confirmed for four weeks 0 days 26 days
Paint and drying line unusable after fire or major damage 15 days 90 days
ERP and MES not available for more than four hours 0 days 12 days
Hall section unusable after roof, water or structural damage 10 days not rated
Power or compressed air station out 1 hour 4 hours

In the example plant, a site for conveyor components, the housing plan reads: release the external machining partner, send drawings and gauges, ship from the ten day buffer. The IT plan reads: print the picking lists of the week, switch shipping to paper, start the restore from the offline backup.

Exercises are the only proof

Four exercises in twelve months, two of them table top and two live, each half a day or less.

In February the team assumed the systems were gone and tried to pick, produce and ship for one shift on paper. Shipping worked. Picking lists were missing for 40 percent of the parts, which would have cost a day. The action was one Friday routine: IT prints the full list every week.

In April the external partner machined twenty housings for real. The target was five days and the exercise showed 6.5, because the partner had no gauges and no current drawings. Both now sit at the partner and are checked twice a year.

In July the generator carried the test benches and the server room in 35 minutes against a target of one hour.

In October the motor scenario was played through on paper. Eight weeks of cover against a ramp of ten weeks leaves fourteen days without deliveries, so the cover is being raised.

Three of the four exercises found something that would have cost days in a real event. An exercise that finds nothing was either perfect or not realistic, and the second is more likely.

Alarm and reporting routes

Who is called first, who informs the customer, who informs the authorities and the insurer, who speaks in public. The list hangs where every shift can see it, names roles with current numbers, and is checked twice a year. Reporting duties are a checkpoint for the responsible function at your site, with a named owner and a date, not something a site team decides on its own.

Findings from exercises and from real events change the plan within four weeks. A plan that has never been exercised is a document with a date on it.