Production Control: Feedback, Disruptions and the Daily Meeting

Control closes the loop between plan and floor with confirmations per shift, a disruption log, a fifteen-minute meeting and four numbers.

A plan without feedback is a wish. The planner releases the week on Friday, and by Tuesday nobody knows which orders are finished, which are stuck and which never started. Control means knowing the state of every order at least once per shift and reacting by clear rules.

Confirmation per shift

Operators or team leaders confirm start, quantity and completion of every order, at least per shift. Where machine and order data flow automatically, check plausibility daily. The goal is simple: the plan and the floor show the same state, every morning.

Log disruptions with time and cause

At the bottleneck, every stop above five minutes is logged with duration and cause. In the valve block plant, four weeks of records at CNC machining showed:

Cause Hours Share
Missing blanks or material 38 33 %
Breakdowns 29 25 %
Missing programs or tools 21 18 %
Quality holds 16 14 %
No operator 12 10 %

116 hours in four weeks, about 8 percent of available bottleneck time. Half of it has causes inside planning: orders released without material, programs or tools. That changes the improvement agenda more than any discussion about machine reliability.

The daily meeting in fifteen minutes

Standing, at the board, every working day:

  • minutes 0 to 2: safety and staffing gaps,
  • minutes 2 to 6: the bottleneck, plan and actual yesterday, what stops it today,
  • minutes 6 to 10: orders in the red buffer zone and customer dates at risk,
  • minutes 10 to 13: rush order requests and what they push back,
  • minutes 13 to 15: escalations and actions with owner and time.

The meeting decides. Status reports belong on the board before it starts.

Escalate in time

Write the triggers down:

  • bottleneck stopped for more than 30 minutes: supervisor and maintenance, immediately,
  • order in the red zone: planner and supervisor, same shift,
  • customer date at risk: production manager and sales, same day,
  • capacity gap above 5 percent for the next two weeks: plant manager, weekly review.

Four numbers

Measure weekly, review monthly:

  • On-time delivery: today 78 percent, target 95.
  • Schedule adherence at the bottleneck: today 81 percent, target 95.
  • Lead time: today 15 working days, target 6.
  • Work in progress: today 2,610 blocks, target 1,050.

Each number has one definition and one owner. In the monthly deviation review, the three largest causes of deviation get an action with a date.

Tools last

Planning systems, real-time machine data and AI assistants help, as long as the basics are in place. A scheduling tool on a full floor with wrong master data only calculates the chaos faster. Introduce release rules, buffers and the daily meeting first. Then let the tools do what they do best: calculate, display and remind. People still decide.