In many plants, an order is released when the material arrives. The logic seems sound: why let material sit in the warehouse when machines could start? The result is a shop floor full of orders that cannot finish, because a program, a tool or a second component is missing.
Release is where planning decides how full the floor will be. It deserves a rule.
The release check
Before an order enters the floor, five things are confirmed:
- Material: blanks and purchased parts physically available, not only booked.
- Tools and programs: fixtures, tools and CNC programs ready and released.
- Capacity: a slot in the bottleneck schedule, and work in progress below the limit.
- Documents: current drawings, test specifications, packing instructions.
- Quality: no open quality hold on the product.
In the example valve block plant, about half of the hours lost at the bottleneck came from orders released without material, programs or tools. A release check costs the planner a few minutes per order. It saves the bottleneck hours.
CONWIP
CONWIP stands for constant work in progress. A fixed number of cards or slots circulates between the first operation and shipping. A new order may only start when a finished one releases its card.
The example plant sets its limit at 1,050 valve blocks, about 42 lots of 25. With 960 blocks in progress, the next candidates are checked in priority order:
- a small block lot, ready: released, 985 in progress,
- a medium block lot, program missing: held,
- a large block lot, ready: released, 1,005,
- a small block lot, blanks missing: held,
- a medium block lot, ready: released, 1,030,
- the next small block lot, ready: held, because it would exceed the limit.
The rule is mechanical, and that is its strength. Nobody negotiates with a full loop.
Rush orders
Rush orders are not the problem. Unlimited rush orders are. Set a weekly limit, for example five orders or 5 percent of bottleneck capacity, and decide each one in the daily meeting together with the orders it pushes back. In the example plant, rush orders fell from about 20 per week to fewer than five once dates were promised from the load view instead of from a standard lead time in the system.
Other ways to limit
CONWIP fits one main flow with mixed products. Other situations need other limits:
- Kanban for repetitive parts with stable demand, a limit of containers per part,
- Drum, buffer, rope for a clear and stable bottleneck, a limit of buffer time,
- Workload control for job shops with many routings, a limit of released hours per work center.
The principle is always the same: nothing enters the floor that cannot flow. The material can wait in the warehouse, where it is easy to find and costs nothing extra. On the floor it only blocks the orders that matter.