Once the bottleneck is known, the plant needs a control logic that serves it. Drum, buffer, rope is the simplest one that works, and it fits on a whiteboard.
Three elements
- Drum: the detailed schedule of the bottleneck. In the valve block plant, the CNC schedule per machine and shift, five days ahead. It sets the pace for the whole plant.
- Buffer: a span of time in front of the bottleneck. Work arrives about two days before the drum needs it, around 117 hours of CNC work. The buffer absorbs disruptions upstream.
- Rope: the link between the drum and the release of material. The saw cuts blanks 2.5 days before the planned CNC start, not earlier, not later.
A second, smaller buffer protects the customer date: three days between the bottleneck and the promised date for washing, assembly and test.
The buffer is time, not a pile
Many plants already have a pile in front of their bottleneck. Usually it is much larger than needed and unsorted. The buffer in drum, buffer, rope is defined as time and controlled through release. The pile shrinks to what the bottleneck needs, and the orders in it are the right ones.
Buffer management
Divide the buffer time into three zones and watch each order:
| Zone | Buffer used | Action |
|---|---|---|
| Green | up to one third | none |
| Yellow | one to two thirds | locate the order, plan a countermeasure |
| Red | more than two thirds | expedite, record the cause |
An order released on day 2 for a CNC start on day 4.5 has a buffer of 2.5 days. On day 4 it has used 80 percent and is red if it has not arrived. The supervisor acts now, not when the machine stands.
The causes are the improvement list
The most valuable output of buffer management is the list of causes of red orders. In the example plant, four weeks of records showed blanks waiting at washing, programs not released and saw blades changed at the wrong time. These are concrete problems with owners, not general complaints about the shop floor.
Sizing the buffer
Start with about half of the current lead time from release to the bottleneck. Orders took five days to reach CNC machining, so the first buffer was 2.5 days. Then adjust monthly:
- more than 10 percent of orders in the red zone: increase by 10 percent and attack the top cause,
- 3 to 10 percent: keep it, work on causes,
- below 3 percent: reduce by 10 percent and shorten lead time.
Why it works
Drum, buffer, rope does not need a sophisticated system. It needs a schedule for one work center, a release rule and the discipline to look at buffer zones every day. Plants that introduce it typically see two effects within weeks: the bottleneck stops waiting, and work in progress falls because material is no longer released just because it has arrived.