The run at rate is passed, production takes over, the team moves to the next project. Three months later the cell has forty open points, nobody knows where the latest PLC version is, and the next project repeats the same delay with the same supplier.
Projects do not end. They are closed, or they fade out.
Acceptance with criteria
Acceptance follows the criteria in the charter, not the mood of the last week. For an assembly cell they typically include five days at target cycle time and quality with production operators, a safety approval, and trained shifts.
The person named in the charter signs. Defects that do not block acceptance go onto a list with an owner and a date. Acceptance “with open points” is normal. Acceptance with open points that have no owner is not.
Handover is a deliverable
What production and maintenance need on the first day without the project team:
- documentation, drawings and spare parts list,
- software source, the released version and how to change it,
- training records per shift,
- maintenance plan and contacts at the suppliers,
- the open point list with owners.
Plan the handover as a work package with its own definition of done, not as a meeting in the last week.
Close the books
Stop booking on the project, close open orders, write the final cost against the budget and the forecasts. The difference between the forecast in week 16 and the final cost is useful information for the next estimate.
Lessons that change something
Lessons learned often produce a long document that nobody reads. Three rules make them useful:
Collect at every gate, not only at the end, when half the team has left and the early mistakes are forgotten.
Write each lesson as a rule for the next project. “Order drive units after design review 1” helps the next team. “Procurement was difficult” does not.
Change the standard. A lesson counts as learned when the project template, the checklist or the gate criteria have changed. Give each rule an owner and a date for that change.
The benefits review
Many objectives can only be checked months later: cost per unit, quality in series, availability of the cell. Put a benefits review into the calendar before the project closes, with the sponsor, three to six months after handover.
The review closes the loop between the charter and the result. It is also the best preparation for the next charter, because it shows which promises the company can keep and which it should no longer make.