Not all project work comes in work packages or sprints. During design and commissioning, a stream of small items arrives every day: drawing changes, supplier questions, test cases, open points from the factory acceptance test.
Handled by email, these items disappear. Handled on a Kanban board, they flow.
A simple board
Four columns are enough for most teams:
- Ready: clear, estimated, accepted for work. Limit: 8 items.
- In work: one person pulled it, start date written. Limit: 4 items.
- Review and test: checked by a second person against the definition of done. Limit: 3 items.
- Done: accepted, end date written.
The board can be physical in the project room or digital for distributed teams. What matters is that it is the only list. A second list in someone’s notebook breaks the system.
Limit the work in progress
The limits are the core of Kanban. When “in work” holds four items, nobody starts a fifth. The team finishes something first or helps a colleague in review.
This feels slow at the beginning. In practice it shortens lead time, because work no longer waits half-finished while people switch between six topics. Little’s law describes the effect: average lead time equals work in progress divided by throughput. Fewer items in progress at the same throughput means faster delivery.
Measure lead time
Write two dates on every card: when it was pulled and when it was done. The difference is the lead time.
After a few weeks the team can make reliable statements: “85 percent of drawing changes are done within six working days.” This is a better basis for promises than any estimate, and it shows immediately when the flow slows down.
Where it fits in a project
Kanban works well for:
- open points after factory and site acceptance tests,
- change requests below the project manager limit,
- test execution during commissioning,
- support during the first weeks after start of production.
It does not replace the schedule for large deliverables with long lead times. A frame and a drive unit need dates, not a column.
The daily look at the board
Ten minutes in front of the board, once a day, right to left: what is close to done, what is blocked, what waits for review? Start with the items closest to done, because finishing creates value and starting does not.
A board that is updated daily shows the state of the work at a glance. A board that is updated weekly is just another report.