Kanban for Project Teams

A visual board with work in progress limits keeps change requests, tests and drawings flowing, and lead time shows where they stop.

Not all project work comes in work packages or sprints. During design and commissioning, a stream of small items arrives every day: drawing changes, supplier questions, test cases, open points from the factory acceptance test.

Handled by email, these items disappear. Handled on a Kanban board, they flow.

A simple board

Four columns are enough for most teams:

  • Ready: clear, estimated, accepted for work. Limit: 8 items.
  • In work: one person pulled it, start date written. Limit: 4 items.
  • Review and test: checked by a second person against the definition of done. Limit: 3 items.
  • Done: accepted, end date written.

The board can be physical in the project room or digital for distributed teams. What matters is that it is the only list. A second list in someone’s notebook breaks the system.

Limit the work in progress

The limits are the core of Kanban. When “in work” holds four items, nobody starts a fifth. The team finishes something first or helps a colleague in review.

This feels slow at the beginning. In practice it shortens lead time, because work no longer waits half-finished while people switch between six topics. Little’s law describes the effect: average lead time equals work in progress divided by throughput. Fewer items in progress at the same throughput means faster delivery.

Measure lead time

Write two dates on every card: when it was pulled and when it was done. The difference is the lead time.

After a few weeks the team can make reliable statements: “85 percent of drawing changes are done within six working days.” This is a better basis for promises than any estimate, and it shows immediately when the flow slows down.

Where it fits in a project

Kanban works well for:

  • open points after factory and site acceptance tests,
  • change requests below the project manager limit,
  • test execution during commissioning,
  • support during the first weeks after start of production.

It does not replace the schedule for large deliverables with long lead times. A frame and a drive unit need dates, not a column.

The daily look at the board

Ten minutes in front of the board, once a day, right to left: what is close to done, what is blocked, what waits for review? Start with the items closest to done, because finishing creates value and starting does not.

A board that is updated daily shows the state of the work at a glance. A board that is updated weekly is just another report.