A project is not a success when it is closed. It is a success when its benefit shows in the figures of the line. Most plants never look.
Three checks
At gate 4, when the project closes, sponsor and benefit owner confirm the measure, its baseline and the target, and fix three dates.
- After 3 months: is the effect visible in the measure? A first value per year is calculated.
- After 6 months: is the effect stable? If there is a gap, the benefit owner names measures.
- After 12 months: the final value, entered in the budget of the line.
The benefit owner is the line manager who has the result in the budget, not the project manager, who is long since in the next project. The controller confirms each value with the same calculation that was used at gate 2.
The first look back
The example plant had closed five projects in the twelve months before its first portfolio decision. Nobody had checked them. The first check was sobering.
| Project | Planned EUR per year | Confirmed EUR per year |
|---|---|---|
| Torque monitoring in assembly | 120,000 | 85,000 |
| Returnable packaging | 60,000 | 25,000 |
| Coolant filtration in hall 1 | 90,000 | 40,000 |
| Barcode booking at goods receipt | 80,000 | 25,000 |
| Shift model for the paint shop | 60,000 | 5,000 |
| Total | 410,000 | 180,000 |
Only 44 percent of the planned benefit could be confirmed. The five projects had also taken 14 months on average instead of the planned 7.
Lessons that change something
A lesson counts when it changes a template, a rule or an estimate. Otherwise it is only a memory. The plant drew three:
- All five projects took about twice the planned time. Since then, plans at gate 2 are checked against the capacity sheet, not against the wish date.
- Three benefits rested on volumes that did not come. Benefit statements now name the volume they assume, and controlling checks it.
- No benefit had an owner after close. The benefit owner now signs at gate 2 and reports three times.
Seven key figures
The portfolio itself needs numbers. Seven are enough, reviewed by the board once a quarter.
| Key figure | Start | After 12 months |
|---|---|---|
| Active projects | 22 | 5 |
| Load of process engineering | 251 % | 51 % |
| Projects finished in twelve months | 5 | 12 |
| Average lead time of finished projects | 14.0 months | 8.5 months |
| Milestones on date | 41 % | 78 % |
| Benefit confirmed against plan | 44 % | 85 % |
| Projects red for more than 2 months | 3 | 0 |
The load of process engineering stayed near 84 percent for most of the year, and the low values of the last month only mean that the board has room for the next starts from the queue and from new proposals.
None of this needs more people. The capacity in the example stayed at 153 person-days per month the whole year. What changed is the number of projects that shared it, and the habit of asking, twelve months after the applause, whether the benefit arrived.