Somebody has to keep the register, count the capacity, prepare the board and look after the templates. In a group with hundreds of projects that is a department, the project management office or PMO. In a plant with 22 projects it is a role, and it should stay one.
What the project office does, and what it does not
| The project office does | It does not |
|---|---|
| Keep the register and the capacity sheet up to date | Manage projects |
| Collect the status reports and build the overview | Decide on start, stop or rank |
| Prepare the board and keep the decision log | Rewrite the reports of the project managers |
| Provide the templates and train new project managers | Ask for data that nobody uses |
| Track dependencies, the shutdown calendar and benefit checks | Own the benefit |
Three forms
Supporting. The office offers templates, advice and an overview. Using them is voluntary. This fits the first months and very small sites.
Coordinating. The office keeps register, capacity and gates, and the standards are binding for every project. This fits sites with 10 to 60 projects and is the form of this series.
Directing. The office employs the project managers and runs the large projects itself. This fits large organizations with full-time project managers.
The setup of the example plant
- Register owner and board preparation: an industrial engineer on the staff of the plant manager, with half of a full-time position.
- Benefit figures and budget: the plant controller, two days per month.
- Coach for new project managers: one experienced project manager, one day per month.
That is well under one position in total, for a portfolio of EUR 2.4 million of budget and EUR 2.1 million of planned benefit per year.
One detail is easy to get wrong. The register owner should not be one of the bottleneck engineers. Taking half a process engineer for the role would remove 9 of the 45 person-days per month on which most projects wait.
The monthly work
In the last week of the month the register owner collects three figures per active project, updates remaining person-days and months, and repeats the walk down the ranking for the capacity that became free. Before the board, the overview, the red and yellow reports, the gate checklists and the open decisions go to the members. After the board, the decisions go out on the same day.
Support, not bureaucracy
Three rules keep the role lean.
Six templates, not sixty. Proposal, plan, status report, gate checklist, change request and closure report. Everything else is the business of the project manager.
One hour per project and month. If reporting takes a project manager longer than that, the template is too long. More reporting needs the approval of the plant manager.
Every field has a reader. Once a year each field of each template is checked. A field that nobody in the board reads is deleted.
There is a simple test for whether the project office is seen as help. Ask the project managers what they get from it. Good answers are: I know when my people are free, my gate was prepared, somebody told me that the other project needs the same hall. A bad answer is: another report.
When to grow
The role needs more time when the portfolio grows beyond what one person can know. Until then, the best investment is not more staff for the office. It is the discipline of the board to start fewer projects, which makes the register shorter, the conflicts fewer and the reports easier to read.